Bill Walker Pool roofing Project
The 2003 bond Walker Pool Dressing Rooms Roofing Project Upgraded and/or Maintained Existing Roofs to a Uniform District Standard.
Planning Estimate1: $180,000
Architect: Wiss, Janney, Elstner Associates, Inc.
General Contractor: Mahone Roofing and Sheet Metal Co., Inc.
Pictures: Aerial
Project Summary:
- Bid Award Agenda Item (PDF)
- Bid Tab (PDF)
Construction Bonds | CM&E Home
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.