This project addressed the Thousand Oaks ES Re-Roofing and Roof-Related Work Project, which included replacement of the main building roof covering an area measuring approximately 76,599 sq. ft.

Planning Estimate1: $2,256,550

Start Date: March 2009

End Date: November 2009

Architect: Wiss, Janney, Elstner Associates, Inc.
Wiss, Janney, Elstner Associates, Inc. - San Antonio

General Contractor: Beldon Roofing Company
Beldon Roofing Company - San Antonio

Pictures: Aerial

Project Summary: (PDF Format)

Construction Bonds | CM&E Home

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.