Larkspur ES Re-Roofing and Roof-Related Work

The 2010 QSCB Program included funding to address the Larkspur Elementary School Roof Replacement and Roof-Related Work Project, which includes a total roof replacement area of approximately 53,388 sq. ft.

Planning Estimate1: $1,135,000

Start Date: June 22, 2011

End Date: October 9, 2011

Architect: Wiss, Janney, Elstner Associates, Inc.
Wiss, Janney, Elstner Associates, Inc. - San Antonio

General Contractor: Port Enterprises

Pictures: Aerial/Architectural

Project Summary: (PDF Format)

Construction Bonds | CM&E Home

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.