Larkspur ES Re-Roofing and Roof-Related Work
The 2010 QSCB Program included funding to address the Larkspur Elementary School Roof Replacement and Roof-Related Work Project, which includes a total roof replacement area of approximately 53,388 sq. ft.
Planning Estimate1: $1,135,000
Start Date: June 22, 2011
End Date: October 9, 2011
Architect: Wiss, Janney, Elstner Associates, Inc.
General Contractor: Port Enterprises
Pictures: Aerial/Architectural
Project Summary: (PDF Format)
Construction Bonds | CM&E Home
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.