Camelot ES Roofing Replacement

The 2003 Bond Program includes funding to replace the roof installed in 1987 at the Camelot Elementary School cafetorium and central plant building over an area measuring 8,795 square foot.

Planning Estimate1: $113,209

Start Date: March 27, 2006

End Date: June 18, 2006

Architect: Edis Oliver and Associates, Inc.

General Contractor: Port Enterprise, Ltd.

Project Summary:

Construction Bonds | CM&E Home

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.