White MS Roofing Program
The 2007 Bond Program includes funding for Phase I - Replace the second floor roofs of the main building at White Middle School measuring approximately 40,700 sq. ft. Phase II - Includes a roof replacement area of 32,198 sq. ft.
Planning Estimate1: $2,185,550
Start Date: June 7, 2010
End Date: August 26, 2010
Architect: Wiss, Janney, Elstner Associates, Inc.
General Contractor: Phase 1: Port Enterprises Phase 2: Port Enterprises
Pictures: Aerial
Project Summary: (PDF Format)
- Phase 1 - Bid Award Agenda Item
- Phase 1 - Bid Tab
- Phase 2 - Bid Award Agenda Item
- Phase 2 - Bid Tab
Construction Bonds | CM&E Home
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.