Nimitz MS Campus Upgrade

Campus Upgrade to include: (1) a new 14-classroom addition to replace 7 portable classroom buildings; (2) athletic facility replacement; (3) administrative, counseling, and clinic addition; (4) fine arts orchestra program addition; (5) teacher resource support areas; (6) tennis courts replacement; (7) central plant facility upgrades to support the new campus additions; (8) landscaping, irrigation, drainage, site utilities, and infrastructure improvements to complement the new facility additions; and (9) selective building demolition.

This project included the following Bid Packages: Bid Package I: Campus Drainage Improvements Bid Package II: New Academic Facilities and Campus Renovations

Planning Estimate1: $28,500,000

Start Date: February 2014

End Date: June 2016

Architect: O'Neill Conrad Oppelt Architects Inc. (OCO)
O'Neill Conrad Oppelt Architects Inc. (OCO) - San Antonio

General Contractor: Joeris General Contractors, Ltd.
Joeris General Contractors, Ltd. - San Antonio

Pictures: Aerial/Architectural

Project Summary: (PDF Format)

Construction Bonds | CM&E Home

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.