Jackson MS Roofing Program

The 2003 Bond Program included funding to replace the roof installed in 1973 at the Jackson Middle School main academic building over an area measuring approximately 85,000 sq. ft.

Planning Estimate1: $1,703,944

Start Date: June 1, 2004

End Date: September 22, 2004

Architect: Edis Oliver and Associates, Inc.

General Contractor: Bentley Sheet Metal and Roofing

Pictures: Aerial/Architectural

Project Summary:

Construction Bonds | CM&E Home

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.