Bradley MS Roofing Program
The 2007 Bond Program includes funding to provide for replacement of approximately 46,238 sq. ft. of existing facility roof with a new built-up roof, including overflow drains, additional roof insulation, curbs for mechanical equipment and minor piping modifications to facilitate the roof replacement.
Planning Estimate1: $1,491,600
Start Date: May 21, 2010
End Date: September 2010
Architect: Wiss, Janney, Elstner Associates, Inc.
General Contractor: Beldon Roofing
Project Summary:
- Construction Document (CD) Approval (PDF)
- Bid Award (PDF)
- Bid Tab (PDF)
Construction Bonds | CM&E Home
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.