Reagan HS Fine Arts and JROTC Facility Additions and Renovations Project
The 2015 Bond Program included funding at Reagan High School to construct new Fine Arts and JROTC Facility Additions and provide for selective interior Renovations. The bond program provided for construction of the following program elements: (1) new Fine Arts Facility addition and renovations including a new 2nd band rehearsal hall, band office, and band storage area, a new 2nd orchestra rehearsal hall, orchestra office, and orchestra storage area; and a shared ensemble room. The Fine Arts Facility addition was constructed adjacent to the existing band and orchestra program areas to provide connectivity between the existing band and orchestra program areas and new fine arts facilities. The design program for Fine Arts Facility addition equaled 7,400 sq. ft. of facility improvements. Following construction of the new fine arts addition, the existing band rehearsal hall received interior renovations as the space was over 20 years old; (2) New JROTC Facility Addition with main entry lobby, staff offices and cadet workroom/office area; 2 JROTC classrooms with operable folding accordion partition; drill and arms room storage; supply room; men’s and women’s locker rooms; laundry room; ice machine room; 8-lane rifle range with control booth, observation area, bleacher seating and new SIUS Targeting System. The JROTC Facility Addition was constructed adjacent to the existing JROTC drill marching pad. The design program for the JROTC Addition equals 12,700 sq. ft. of facility improvements; and (3) The Career & Technical Education Business INCubator Project consisted of renovating the existing campus JROTC rifle range into a collaborative business educational instructional space for entrepreneurs and business ideas. The project was split-funded by the 2015 Bond ($134K) and CTE Programs ($138.7K). The project consists of a business collaboration lab, two small conference rooms, one large conference room, a maker space, and business office.
Planning Estimate1: $8,750,000
Start Date: May 2018
End Date: October 2019
Architect: Alamo Architects
General Contractor: Guido Brothers Construction Company
Pictures: Aerial/Architectural
Project Summary: (PDF Format)
- Schematic Design Approval
- Board of Trustees Schematic Design Presentation - June 12, 2017 (9 MB)
- Construction-Manager-at-Risk Selection Bid Award | Bid Tab
- Bid Authorization - February 12, 2018
- Bid Award | Construction Cost Bid Summary | Subcontractor Bid Summary
Construction Bonds | CM&E Home
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.