Return to Headlines

Ridgeview ES Re-Roofing and Roof-Related Work Project

The 2015 Bond Program included funding to replace selected roofed areas at seven (7) District facilities as part of the District’s planned Roof Replacement Program. Facilities included in the 2015 Bond Roofing Construction Program include: Lee High School; Krueger Middle School (transferred to the hail damage claim); and Clear Spring, Northwood, Ridgeview, Serna, and Stahl Elementary Schools. Typical roof life expectancies range from 20 to 30 years based upon several factors, which include: (1) quality of the roof product and construction installation; (2) wear and tear due to foot traffic for operations and maintenance access to rooftop equipment; and (3) long-term weather conditions and resultant impacts. This project addressed the Ridgeview Elementary School Re-Roofing and Roof-Related Work Project, which includes a total roof replacement area of 8,040 sq. ft.

Planning Estimate1: $295,000

Architect: Wiss, Janney, Elstner Associates, Inc.

General Contractor: Turner Roofing

Pictures: Aerial

Project Summary: (PDF Format)

Construction Bonds | CM&E Home

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.