Comalander Stadium Facility Upgrades

Bid Package 1 Bleacher Replacement

The 2015 Bond Program includes funding to provide facility upgrades at the Comalander Stadium to (1) replace the existing east and west side bleachers (The east side stands were replaced between December 2016 and July 2017, while the west side stands were replaced between December 2017 and July 2018.); (2) construct two new field house locker rooms for the home and visitor teams; and (3) renovate the existing public restrooms located under the east/west bleachers.

Planning Estimate1: $3,275,000

Start Date: December 2016

End Date: July 2018

Architect: RVK Architects

General Contractor: Southern Bleacher Company

Pictures: Aerial/Architectural

Project Summary:


Bid Package 2 Bleacher Demolition and Utilities Reconnection

The Bid Package 2 Bleacher Demolition and Utilities Reconnection Project will disconnect the existing utilities tied to the underside of the existing bleachers (i.e., mechanical, electrical, plumbing, and technology systems), demolish and remove the existing bleacher structural frame, seats, and ramps, and – following installation of the new bleacher system – reconnect utilities to reactivate all existing facility support systems.

Planning Estimate1: $1,045,000

Start Date: December 2016

End Date: June 2017

Architect: RVK Architects

General Contractor: Whiting-Turner Contracting Company

Pictures: Aerial/Architectural

Project Summary:


Bid Package 3 New Field Maintenance Building Project

The 2015 Bond Program includes funding to provide facility upgrades at BAC Comalander Stadium. This project will relocate and replace the existing field maintenance building (2,500 sq. ft.) with a new metal building and outdoor covered work area. Construction of the new field maintenance building will occur between the baseball facility north-side visitor stands and Comalander Stadium.

Planning Estimate1: $1,175,000

Start Date: June 2017

End Date: January 2018

Architect: RVK Architects

General Contractor: F.A. Nunnelly Company

Pictures: Aerial/Architectural

Project Summary:


Bid Package 4 New Field House Locker Rooms and Stadium Restroom Renovations

BAC Comalander Stadium New Field House

Bid Package 4 will construct 2 new field house locker rooms (home and visitor) at the south end of the stadium to replace the existing locker rooms located under the east/west bleachers, renovate the men’s and women’s public restrooms which serve Comalander Stadium, and provide various site infrastructure improvements to support the project. The total facility program for Bid Package 4 equals 13,392 sq. ft. which includes 10,992 sq. ft. for 2 new field houses and 2,400 sq. ft. for the stadium restroom renovations.

Planning Estimate1: $5,616,000

Start Date: December 2017

End Date: August 2018

Architect: RVK Architects

General Contractor: Joeris General Contractors

Pictures: Aerial/Architectural

Project Summary:

Construction Bonds | CM&E Home

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.