Bradley MS Additions and Renovations Project
The 2015 Bond Program includes funding for Bradley Middle School to construct a 2nd band hall in support of the fine arts program and expand the campus cafeteria facility. The 2015 Bond will provide for construction of the following program elements: (1) new band hall addition with Wenger practice rooms, instrument storage area, and office connected to the existing fine arts facility; (2) cafeteria dining area expansion with new stage area, control booth, and chair storage area; (3) drama program relocation/construction with black box theater/classroom, office, and storage area; (4) secure entry vestibule at the main campus entrance; (5) existing band hall renovations (flooring, painting, and LED lighting); (6) new men’s and women’s restrooms to support the expanded cafeteria dining area; and (7) landscaping, irrigation, drainage, site utilities, and infrastructure improvements to complement the new facility additions. The design program for the 2015 Bond Bradley Middle School Additions and Renovations Project equals 27,285 sq. ft. of facility improvements, including 19,345 sq. ft. of facility additions and 7,940 sq. ft. of interior renovations. Additionally, an enclosed connecting corridor to the new fine arts addition (715 sq. ft.) will be included in the project as a design-bid alternate.
Planning Estimate1: $ 8,750,000
Start Date: October 2017
End Date: March 2019
Architect: McChesney/Bianco Architecture
General Contractor: Bartlett Cocke General Contractors
Pictures: Aerial/Architectural
Project Summary:
- Construction-Manager-at-Risk Selection Bid Award (PDF)
- Schematic Design Approval (PDF)
- Board of Trustees Schematic Design Presentation - December 12, 2016 (PDF - 7 MB)
- Bid Authorization (PDF)
- Bid Award (PDF) | Construction Cost Bid Summary (PDF) | Subcontractor Bid Summary (PDF) | Value Engineering Summary (PDF)
Bradley Middle School Construction Progress - April 13, 2018
Construction Bonds | CM&E Home
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.