Return to Headlines

Montgomery ES Gymnasium Replacement

The 2015 Bond Program included funding to provide renovations to the existing gymnasium facility at Montgomery Elementary School. An assessment of the existing gymnasiums early-on in the design process by the AE Team revealed that the District would be better served by replacing the existing athletic facility with the District’s new elementary school gym(+) design rather than providing interior renovations to the existing athletic facility. The existing gymnasium areas were assessed to be substandard and undersized with low ceilings.

Planning Estimate1: $1,125,000

Start Date: May 2019

End Date: March 2020

Architect: Shawn Kaarlsen & Associates and C. J. Lammers & Associates

General Contractor: Baron-Long Construction

Pictures: Aerial/Architectural

Project Summary: (PDF Format)

Construction Bonds | CM&E Home

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.