2007 Bond Project: Garner Middle School Fine Arts Addition and Auditorium Renovation

This project provides for both new construction and renovation elements, including: (1) construction of a new Fine Arts facility to replace the existing choir room (original construction – 1961) and orchestra portable classroom building, (2) renovation of the auditorium and stage areas, (3) construction of a new competition gymnasium (replacing the existing auxiliary gymnasium), (4) construction of a compliment of locker room and office areas to support the new gymnasium area, (5) installation of HVAC systems in the existing locker room areas, and (6) installation of related civil site infrastructure to support the programmed construction.
Planning Estimate1:
$ 7,745,000
Start Date:
December 15, 2008
End Date:
July 30, 2010

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.