2010 QSCB Project: Bradley Middle School Roofing Program

This project addresses the Bradley Middle School Re-Roofing and Roof-Related Work Project which includes a total roof replacement area of approximately 41,525 sq. ft.
Planning Estimate1:
$ 905,000
Start Date:
June 24, 2012
End Date:
August 17, 2012
Photo Gallery:
General Contractor:
Project Summary :

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.