Madison High School Construction Projects
Madison High School Bond Projects

Esser-III
Madison HS Central Plant Chiller Replacement
ESSER-III Funds are available to replace the chillers at the Madison High School central plant during the 2022 summer period. This project will replace three existing 400-ton chillers with three new 500-ton chillers. As a result of the increased chiller capacity, the central plant chiller yard must be expanded and reorganized to provide appropriate chiller separation for proper air flow circulation and operation.
Planning Estimate1: $2,200,000
Start Date: March 2022
End Date: August 2022
Architect: MEP Engineering
General Contractor: Marksmen General Contractors
Project Summary: (PDF Format)
2015 Bond
Madison HS JROTC Facility Additions and Renovations
The 2015 Bond Program included funding at Madison High School to upgrade the existing JROTC Facility which was initially constructed as part of the 1998 Bond Program. The 2015 Bond Program provided several facility additions which allowed for the complete reorganization of the interior spaces and following program elements: (1) two JROTC classrooms with operable folding accordion partition; (2) men’s and women’s locker rooms with dressing and shower areas; (3) staff offices and cadet workroom/office area; (4) installation of a high-density mobile storage system in the supply room ; (5) an observation viewing area with bleacher seating in the 8-lane rifle range; (6) a control booth for the 8-lane rifle range to manage the new SIUS Targeting System; and (7) selective interior renovations throughout the remainder of the facility to effectively merge the new facility additions with the existing floor plan. The design program for the 2015 Bond Madison High School JROTC Facility Additions and Renovations Project equals 12,136 sq. ft. of facility improvements, including 4,384 sq. ft. of facility additions and 7,752 sq. ft. of interior renovations.
Planning Estimate1: $2,175,000
Start Date: April 2018
End Date: September 2019
Architect: Garza Architects, Inc.
General Contractor: F. A. Nunnelly Construction Company
Pictures: Aerial/Architectural
Project Summary (PDF Format):
- Schematic Design Approval - February 13, 2017
- Board of Trustees Schematic Design Presentation - February 13, 2017 (4 MB)
- Bid Authorization Approval - December 11, 2017
- Pre-Proposal Conference (January 31, 2018) - Presentation (6 MB), Sign-In Sheet
- Bid Award | Bid Tab (March 26, 2018)
- Kick-Off Conference (April 12, 2018) - Presentation (9 MB)
Madison HS JROTC Facility Air-Rifle Electronic Target and Scoring System Upgrades
Learn more about the Air-Rifle Electronic Target and Scoring System Upgrades Project (4 Campuses) at 2015 Specialty Bond Projects.
Madison HS Special Education Restroom Renovations
Learn more about the #5.11 Special Education Restroom Renovations Project (14 Campuses) at 2015 Specialty Bond Projects.
Madison HS Keyless Access Control and Video Surveillance Camera Upgrades
Learn more about the Campus Keyless Access Control and Video Surveillance Camera Upgrades Project (69 Campuses) at 2015 Specialty Bond Projects.
Madison HS Football Field Upgrade to Artificial Turf
Learn more about the High School Sports Fields (Upgrade Main Football Field to Artificial Turf) and Athletic Tracks Life-Cycle Maintenance Projects at 2015 Specialty Bond Projects.
2007 Bond
Madison HS Athletic & Fine Arts Additions / Renovations
The 2007 Bond Program included funding for a phased construction approach which included: (1) construction of a new Fine Arts facility, (2) construction of a new Athletic Facility, (3) relocation and reconstruction of the existing soccer field and practice football field to facilitate the optimal location for siting the new Athletic Facility, (4) relocation of reconstruction the existing six tennis courts to facilitate the optimal location for siting the new Fine Arts Facility, (5) demolition of the existing auditorium and construction of a new outdoor courtyard adjacent to the new Fine Arts facility, (6) construction of an outdoor concession stand and restroom facility adjacent to the new Athletic Facility to service the competition athletic fields, (7) construction of parking lots, fire lanes and associated hardscape to support both new facilities, and (8) site landscaping and irrigation.
Planning Estimate1: $32,625,000
Start Date: April 13, 2009
End Date: March 1, 2011
Architect: Pfluger Associates Architects
General Contractor: Joeris General Contractors, Ltd.
Pictures: Aerial/Architectural
Project Summary (PDF Format):
2003 Bond
Madison HS Classroom Addition
The 2003 Bond Program included funding for a major classroom addition: New Academic Areas (New Science Department with 14 Science Classrooms/Labs, 7 Prep/Storage Rooms, and 1 Departmental Teacher Resource Center; Renovate / Convert Existing Science Labs to Classrooms "as needed"; and 1 New Computer Science Lab), New Kitchen & Cafeteria Dining Area (Build New Kitchen in lieu of renovation, Build New Cafeteria Dining Area in lieu of renovation, and Re-develop New Outside Courtyard Dining Areas), Site Work & Hardscape Improvements (Relocate Bus Loop Area, Construct Covered Walkway for Student Drop Off / Pick Up, and Construct New Entry Plaza with Covered Walkways at Parent Loop for Drop Off / Pick Up), Construct New Band Marching Area in lieu of renovation, and Construct Additional Satellite Parking Lot (Expand Campus Parking Capacity by Constructing New Parking Area in vicinity of Athletic Fields)
Planning Estimate1: $18,160,000
Start Date: July 2005
End Date: August 2007
Architect: Pfluger Associates Architects
General Contractor: Bartlett Cocke General Contractors
Pictures: Aerial/Architectural
Project Summary (PDF Format):
Madison HS Roofing Program
Phase 1
The 2003 Bond Program includes funding for roofing Improvements to upgrade and/or Maintain Existing Roof to a Uniform District Standard. This project represents Phase one of a two phase project to replace the remainder of the original Madison High School roof areas. Phase 1 will replace the roof area over the Auditorium Building measuring approximately 16,793 sf.
Planning Estimate1: $3,179,308 (Complete Project)
Start Date: February 2005
End Date: April 2, 2005
Architect: Edis Oliver and Associates
General Contractor: Mahone Roofing and Sheet Metal Company
Project Summary:
- Bid Award (PDF)
Phase 2-A
The 2003 Bond Program includes funding for roofing Improvements to upgrade and/or Maintain Existing Roof to a Uniform District Standard. This project will replace direct expansion natural gas heating RTUs in the H-Building and like units in the K-Building that are operating at or beyond the typical life expectancy for this type equipment. In addition, a portion of the K-Building 1st floor roof and deck will be replaced in conjunction with the rooftop unit replacements.
Start Date: June 1, 2006
End Date: August 1, 2006
Architect: MEP Engineering, Inc.
General Contractor: Comfort Air Engineering, Inc.
Project Summary:
Phase 2-B
The 2003 Bond Program includes funding for roofing Improvements to upgrade and/or Maintain Existing Roof to a Uniform District Standard. This project represents the final phase of a multi-phase project to replace the original roof areas at Madison High School. Phase II-B replaces the remainder of the H and K Building roof areas (53,314 sq. ft.).
Start Date: December 2006
End Date: 2007
Architect: Edis Oliver & Associates, Inc.
General Contractor: Mahone Roofing and Sheet Metal Co., Ltd.