Transportation North Bus Satellite Facility
Bid Package 1
Bid Package 1: Security fence along Highway 281
Planning Estimate1: $225,000
Start Date: November 2009
End Date: February 2010
Architect: Pape-Dawson Engineers
General Contractor: A. Vasquez Construction Co., Inc.
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.
Bid Package 2
Bid Package 2: Facility Renovations, Site Landscaping and Civil Site Improvements
Planning Estimate1: $975,000
Start Date: Winter 2009
End Date: August 1, 2010
Architect: Pape-Dawson Engineers
General Contractor: F.A. Nunnelly Company
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.
Bid Package 3
Bid Package 3: Site Access Road Construction and Marshall Road Civil Engineering Improvements
Planning Estimate1: $1,280,000
Architect: Pape-Dawson Engineers
General Contractor: DNT Construction
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.
Bid Package 4
Bid Package 4: Bus Wash Facility. This project will construct a new automated bus washing system at the Transportation North Facility which will provide an efficient and functional method to wash and maintain the district’s buses and small vehicle fleet along the northern sector of the District. This bus wash facility will include: (1) an automated energy efficient four brush washing system, (2) water reclamation system, (3) storage area for wash equipment, (4) restrooms, (5) exterior power wash station and (6) electrical closet to support future fueling station facility.
Planning Estimate1: $1,023,000
Architect: Parsons Brinckerhoff
General Contractor: Pletz Construction, LLC
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.
Bid Package 5
Bid Package 5: Fueling Station
Planning Estimate1: $500,000
Architect: Pape-Dawson Engineers
General Contractor: Alpha Building Corporation
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.