Bradley Middle School, North East ISD, (NEISD) San Antonio, Texas
Bradley Middle School
14819 Heimer Road
San Antonio, TX 78232
Map / Directions
Aerial/Architectural Photos

2015 Bond

Bradley MS Additions and Renovations Project

Rendering of Bradley MS Additions and Renovations Project.

The 2015 Bond Program includes funding for Bradley Middle School to construct a 2nd band hall in support of the fine arts program and expand the campus cafeteria facility. The 2015 Bond will provide for construction of the following program elements: (1) new band hall addition with Wenger practice rooms, instrument storage area, and office connected to the existing fine arts facility; (2) cafeteria dining area expansion with new stage area, control booth, and chair storage area; (3) drama program relocation/construction with black box theater/classroom, office, and storage area; (4) secure entry vestibule at the main campus entrance; (5) existing band hall renovations (flooring, painting, and LED lighting); (6) new men’s and women’s restrooms to support the expanded cafeteria dining area; and (7) landscaping, irrigation, drainage, site utilities, and infrastructure improvements to complement the new facility additions. The design program for the 2015 Bond Bradley Middle School Additions and Renovations Project equals 27,285 sq. ft. of facility improvements, including 19,345 sq. ft. of facility additions and 7,940 sq. ft. of interior renovations. Additionally, an enclosed connecting corridor to the new fine arts addition (715 sq. ft.) will be included in the project as a design-bid alternate.

Planning Estimate1: $ 8,750,000

Start Date: October 2017

End Date: March 2019

Architect: McChesney/Bianco ArchitectureMcChesney/Bianco Architecture - San Antonio

General Contractor: Bartlett Cocke General ContractorsBartlett Cocke General Contractors - San Antonio

Pictures: Aerial/Architectural

Project Summary (PDF Format):

 Construction Progress at Bradley Middle School, picture taken April 13, 2018
Bradley Middle School Construction Picture - April 13, 2018

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.

Bradley MS Athletic Track Upgrade to All-Weather Surface System

Learn more about the Middle School Athletic Tracks Upgrade to All-Weather Surface Systems Projects at 2015 Specialty Bond Projects.

Bradley MS Keyless Access Control and Video Surveillance Camera Upgrades

Learn more about the Campus Keyless Access Control and Video Surveillance Camera Upgrades Project (69 Campuses) at 2015 Specialty Bond Projects.

2010 QSC Bond

Bradley MS Roofing Program

This 2010 QSCB project addresses the Bradley Middle School Re-Roofing and Roof-Related Work Project which includes a total roof replacement area of approximately 41,525 sq. ft.

Planning Estimate1: $905,000

Start Date: June 24, 2012

End Date: August 17, 2012

Architect: Wiss, Janney, Elstner Associates, Inc.Wiss, Janney, Elstner Associates, Inc. - San Antonio, Texas

General Contractor: Cram Roofing

Project Summary:

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.

2007 Bond

Bradley MS New Athletic Facility

The 2007 Bond Program includes funding to retrofit all Secondary School Athletic/PE and Dance Areas throughout the District with HVAC systems.
  • Add HVAC to Existing Competition Gym and Locker Room Areas
  • Add Large Ceiling Mounted Fans for Air Distribution
  • Replace Existing Metal Gym with New Masonry Gym Facility (Revised)
  • Add Multi-Purpose Classroom to Replace Lost Shop Area (New)
  • Provide Office Area for Coaches and Gym Storage (New)
  • Add Weight Room adjacent to New Competition Gym (New)

Planning Estimate1: $5,028,463

Start Date: June 7, 2010

End Date: July 31, 2011

Architect: Silber & Associates

General Contractor: Joeris General Contractors, Ltd.Logo for Joeris General Contractors

Pictures: Aerial/Architectural

Project Summary:

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.

Bradley MS Roofing Program

The 2007 Bond Program includes funding to provide for replacement of approximately 46,238 sq. ft. of existing facility roof with a new built-up roof, including overflow drains, additional roof insulation, curbs for mechanical equipment and minor piping modifications to facilitate the roof replacement.

Planning Estimate1: $1,491,600

Start Date: May 21, 2010

End Date: September 2010

Architect: Wiss, Janney, Elstner Associates, Inc.Wiss, Janney, Elstner Associates, Inc. - San Antonio, Texas

General Contractor: Beldon Roofing

Project Summary:

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.

Bradley MS HVAC Upgrades for P.E./Athletic/Fine Arts Extracurricular Facilities

Learn more about the HVAC Upgrades for P.E./Athletic/Fine Arts Extracurricular Facilities at 2007 Specialty Bond Projects.

2003 Bond

Bradley MS Science Addition

The 2003 Bond Program includes construction of a Science Lab Facility: 8 Science Labs, 1 Centralized Chemical Storage Area, 3 Preparatory Storage Areas (1 adjacent to each Grade-Level), 2 Faculty Restrooms Upgraded, Science Department Offices (1 Office 1 Workroom), Safety Equipment integrated in Labs and Prep Areas, Connect New One-Story Prototype Facility to existing Facilities through a Covered Walkway.

Planning Estimate1: $4,675,362

Start Date: January 2006

End Date: December 2007

Architect: O'Neill Conrad Oppelt Architects Inc.Oco architects

Architect: Garza Bomberger & AssociatesGarza Bomberger and Associates - San Antonio

General Contractor: Bartlett Cocke General ContractorsBartlett Cocke General Contractors - San Antonio

Project Summary:

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.

>>>Previous Bradley Middle School Bond Projects<<<