Serna Elementary School Construction Projects

2569 NE Loop 410
San Antonio, TX 78217
Map / Directions
Aerial/Construction Photos
2015 Bond
Serna ES Roofing Maintenance
The 2015 Bond Program included funding to replace selected roofed areas at seven (7) District facilities as part of the District’s planned Roof Replacement Program. Facilities in the 2015 Bond Roofing Construction Program include: Lee High School; Krueger Middle School; and Clear Spring, Northwood, Ridgeview, Serna, and Stahl Elementary Schools. Typical roof life expectancies range from 20 to 30 years based upon several factors, which include: (1) quality of the roof product and construction installation; (2) wear and tear due to foot traffic for operations and maintenance access to rooftop equipment; and (3) long-term weather conditions and resultant impacts. This project addresses the Serna Elementary School Roof Replacement and Roof-Related Work Project, which included a total roof replacement area of 8,950 square feet.
Planning Estimate1: $225,000
Start Date: August 2016
End Date: October 2016
Architect: Wiss, Janney, Elstner Associates, Inc.
General Contractor: Turner Roofing Co.
Pictures: Aerial/Architectural
- Construction Document and Bid Delivery Method Approval (PDF)
- Bid Award (PDF)
- Bid Tab (PDF)
Serna ES Maintenance and Repair for Parking Lots and Drop-Off /Pick-Up Lanes
The 2015 Bond Program included funding for maintenance and repair of parking lots and/or drop-off and pick-up lanes at two District campuses (Ridgeview and Serna Elementary Schools) as part of the District's 2015 Bond Asphalt Paving Maintenance and Repair Program. The District maintains approximately 15,500,000 square feet of paved asphalt parking surfaces. Asphalt parking surfaces require periodic maintenance and repair as a result of varying geological soil conditions underlying campus parking areas, surface wear and tear from vehicular traffic, and annual weather conditions. This project addressed the Serna Elementary School Parking Lot Maintenance and Repair Project.
Planning Estimate1: -
Start Date: -
End Date: -
Architect: -
General Contractor: -
Pictures: Aerial
Project Summary: -
Serna ES New Paved Walking Track
Serna ES Restroom Renovations
Serna ES Parking Lot Lighting Upgrades
Serna ES Keyless Access Control and Video Surveillance Camera Upgrades
2007 Bond
Serna ES Re-Roofing and Roof-Related Work
Typical roof life expectancies range from 20 to 30 years based upon several factors, which include: (1) quality of the roof product and construction installation, (2) wear and tear due to foot traffic for operations and maintenance access to rooftop equipment, and (3) long term weather conditions and resultant impacts. This project addressed the Serna Elementary School Roof Replacement and Roof Related Work Project, which included a roof replacement area of 50,688 sq. ft.
Planning Estimate1: $1,375,000
Start Date: June 7, 2010
End Date: September 30, 2010
Architect: Wiss, Janney, Elstner Associates, Inc.
General Contractor: Port Enterprises
Pictures: Aerial
Serna ES Kitchen Facility HVAC System Upgrades
Serna ES Metal Gym Replacement with Masonry Gym & HVAC
>>>Previous Serna Elementary School Construction Bond Projects<<<
- 1998 Bond Serna ES Summary (PDF)
- 1995 Bond Serna ES Summary (PDF)
Additional Information
NEISD opens 3rd SPARK at Serna Elementary School


Serna's Student Council and band members cut the ribbon at the grand opening.

Students enjoy playing on the covered playground areas.