Vineyard Ranch Elementary School Bond Projects

2015 Bond
Vineyard Ranch ES New Paved Walking Track
Vineyard Ranch ES Keyless Access Control Upgrades
2007 Bond
Vineyard Ranch ES New School
This 2007 Bond funded a new Elementary School with classroom capacity for 1000 students, core facilities capable of supporting 1200 students, and a total facility program of 127,743 square feet. The project included: (1) forty-five general instructional classrooms with grade-level workrooms and book storage areas; (2) one computer lab; (3) 10 pull-out classrooms including, two music rooms, four resource rooms, one speech room, two self-contained rooms and one OTPT room; (4) library and media center; (5) kitchen and cafeteria; (6) two gymnasiums with PE Office and athletic storage; (7) administrative & counseling offices and nurse station; (8) parking facilities for staff and visitors; (9) separate bus loop and parent drop-off / pick-up zone; (10) general playfield; and (11) playground areas supporting both upper grade and kinder programs.
Planning Estimate1: $34,025,000
Start Date: November 15, 2010
End Date: December 7, 2012
Architect: Garza Bomberger & Associates
General Contractor: Summit Builders Construction Company
Pictures: Aerial/Architectural
- Property Map
- Bid Award Agenda Item
- Bid Tab - Base Bid (upon award of only Vineyard Ranch)
- Bid Tab - Combination Bid (upon award of Vineyard Ranch / Knights Cross)
- Project Summary
- Architectural Renderings
- Site Plan
- Floor Plans