Basse-McCullough Sports Fields Lighting and Bleacher Seating Expansion
The 2007 Bond Project for the Lee High School Basse-McCullough Sports Fields includes: (1) lighting both the baseball and softball fields for varsity level competition, (2) adding additional bleachers to provide seating for 500 at each field, (3) constructing a restroom facility on the softball side of the drive to expand the total number of toilet facilities to service the increased seating capacity of the baseball and softball fields (4) providing a concession stand as a part of the new restroom facility, (5) adding a small press box at the baseball and softball fields, similar to press box at the new BAC north soccer field, (6) adding a second batting cage at the baseball field adjacent to the existing batting cage, (7) constructing a bullpen adjacent to the west side baseball dugout, (8) constructing a bullpen adjacent to the left sideline fence at the softball field, and (9) constructing a concrete soil stockpile box for storage of soil.
Planning Estimate1: $1,275,000
Start Date: July 2008
End Date: January 2009
Architect: RVK Architects
General Contractor: Joeris General Contractors, Ltd. 
Project Summary:
Construction Bonds | CM&E Home
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.
