Wood MS Roofing Program

Phase 1

The 2003 Bond Program included funding to upgrade and/or maintain existing roofs to a uniform district standard. Phase I of this roofing project replaced the roof installed in 1981 at the Wood Middle School main academic building 2nd floor over an area measuring approximately 29,081 sq. ft.

Planning Estimate1: $494,377

Start Date: December 2004

End Date: April 2005

Architect: Edis Oliver and Associates, Inc.

General Contractor: Samuel Dean Sheetmetal

Pictures: Aerial

Project Summary:

Phase 2

The remaining roof areas not replaced in Phase I, measuring approximately 66,129 sq. ft., were replaced during Phase II of this project during the summer of 2005.

Planning Estimate1: $1,159,141

Start Date: June 2005

End Date: September 2005

Architect: Wiss, Janney, Elstner Associates, Inc.
Wiss, Janney, Elstner Associates, Inc. - San Antonio

General Contractor: Port Enterprises Ltd.

Pictures: Aerial

Project Summary:

Construction Bonds | CM&E Home

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.