Nimitz MS Auditorium Seating Replacement and Storefront

The 2007 Bond Program includes funding for auditorium Interior upgrades to include: replacing old wooden auditorium seating*, adding a storefront entrance, replacing carpeting, interior painting, and refinishing concrete floor.

*Auditorium seats from the old Madison HS Auditorium were recommissioned (refurbished and reused) at Nimitz MS Auditorium.

Planning Estimate1: $94,620 (Funded through the Madison HS Fine Arts Project)

Start Date: June 8, 2010

End Date: August 2010

Architect: Pfluger Associates Architects
Pfluger Associates Architects - San Antonio

General Contractor: Joeris General Contractors, Ltd.
Joeris General Contractors, Ltd. - San Antonio

Project Summary:

Construction Bonds | CM&E Home

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.