         $ Difference
Project Summary    Plan    Actual    + Over / - Under
Olmos Elementary School
Start Date Mar 2005 Apr 2005 + 1
Completion Date
Sep 2006 Aug 2006   - 1
Total Project Cost $ 4,650,000 $ 6,700,839  $ 2,050,839
Building Only Cost (Constr. Contracts)   $ 5,505,635  
Site & Design Development   $ 747,031  
Building Only Cost per Sq. Ft.   $ 126.20  
Facility Gross Total Sq. Footage   45,484 sf.  
Technology   $ 163,851  
Facility Furniture, Fixtures & Equip.   $ 64,214  
ROCIP   $ 69,101  
Construction Management Services   $ 151,007  
Progress Bar - Current Phase of Construction
Progress Bar - Substantial Completion
Project Team
Logo - Chumney & Assoc. Architect: Chumney & Associates
Logo - Browning Construction General Contractor (GC): Browning Construction Co.
Tom Edwards Project Coordinator, NEISD, Construction Management
Bernard Ciulla MEP Inspector, NEISD, Construction Management
Progress Photos Olmos ES - Progress Photos
Olmos ES Campus: 1103 Allena, San Antonio, TX 78213
 
<Previous Page 1 of 2 Next>
This page was last updated on August 23, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering
at 804-7270, ext. 372, regarding webpage-related issues.