         $ Difference
Project Summary    Plan    Actual     + Over / - Under
Jose M. Lopez Middle School
Start Date Jan 2005 Feb 2005 + 1
Completion Date
Dec 2006 Nov 2006 - 1
Total Project Cost $ 33,050,614 $ 35,864,647  $ 2,814,033
Building Only Cost (Constr. Contracts   $ 29,314,210  
Site & Design Development (35.0 acres)
  $ 2,127,979  
Cost per Sq. Ft.   $ 143.00  
Facility Gross Total Sq. Footage
  205,000 sf.  
Technology   $ 1,004,697  
Facility Furniture, Fixtures & Equip.   $ 2,245,816  
ROCIP   $ 367,922  
Construction Management Services   $ 804,023  
Progress Bar - Current Phase of Construction
Progress Bar - Under Construction
Project Team
Logo - Pfluger Assoc. Project Architect: Pfluger Associates
Logo - Chumney & Assoc. Architect: Chumney & Associates
Logo - Joeris General Contractors General Contractor (GC): Joeris General Contractors
Tom Edwards Project Coordinator, NEISD, Construction Management
Bernard Ciulla MEP Inspector, NEISD, Construction Management
Progress Photos Lopez MS - Progress Photos - Set A
Lopez MS Campus: 23103 Hardy Oak Blvd., San Antonio, TX
 
<Previous Page 1 of 2 Next>
This page was last updated on August 23, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering
at 804-7270, ext. 372, regarding webpage-related issues.