Canyon Ridge ES - Summary -- NEISD.net

Construction Management & Engineering

CM&E Home | Our Mission | 2003 Bond Program Status | Engineering | Warranty | ConstructWare
 
<Previous Page 1 of 2 Next>
Photo - Canyon Ridge ES2003 Bond Status Report Banner
     $ Difference
Project Summary    Plan    Actual      + Over / - Under
Canyon Ridge Elementary School
Start Date Mar 2004 Feb 2004  - 1
Completion Date
Aug 2005 Aug 2005   0
Total Project Cost $ 21,977,817 $ 23,558,127 $1,580,310
Building Only Cost (Constr. Contracts)   $ 20,441,223  
Site & Design Development (17.5 acres)
  $794,919  
Cost per Sq. Ft.   $15007  
Facility Gross Total Sq. Footage
  136,207 sq. ft.  
Technology   $556,339  
Facility Furniture, Fixtures & Equip.   $948,432  
ROCIP   $256,557  
Construction Management Services   $560,657  
Progress Bar - Current Phase of Construction
Progress Bar - Completed
Project Team
Logo - Bradley Architects Architect: Bradley Architects
Logo - Bartlett-Cocke GC General Contractor (GC): Bartlett Cocke General Contractors
Woody Johnson Project Coordinator, NEISD, Construction Management
Jeffrey Hoffman MEP Inspector, NEISD, Construction Management
Progress Photos Canyon Ridge ES - Progress Photos
Canyon Ridge ES Campus: 20522 Stone Oak Parkway, San Antonio, TX 78258
 
<Previous Page 1 of 2 Next>
This page was last updated on August 23, 2006.
Please contact Theresa Gray, Web Master, Construction Management and Engineering
at 804-7270, ext. 372, regarding webpage-related issues