2007 Bond Project: White Middle School Roofing Program

Phase I - Replace the second floor roofs of the main building at White Middle School measuring approximately 40,700 sq. ft.
Phase II - Includes a roof replacement area of 32,198 sq. ft.
Planning Estimate1:
$ 2,185,550
Start Date:
June 7, 2010
End Date:
August 26, 2010
Photo Gallery:
General Contractor:
Phase 1: Port Enterprises
Phase 2: Port Enterprises

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.