2007 Bond Project:
Transportation North Bus Satellite Facility - Bid Package I
Scope: |
Bid Package 1: Perimeter Fencing |
Planning Estimate 1: |
$ 225,000 |
Start/End Date: |
November 2009 / February 2010 |
Photo Gallery: |
Aerial Photos |
Engineer: |
Pape-Dawson Engineers Inc |
General Contractor: |
A. Vasquez Construction Co., Inc. |
Project Summary: |
Property Map (PDF) Bid Award Agenda Item (PDF) Bid Tab (PDF) Project Summary (PDF) Architectural Renderings (PDF) Site Plan (PDF) |
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings (November 2006 through February 2007) for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs. Current Program Costs for each project are summarized in the 2007 Bond Budget Report.