2007 Bond Project:
Thousand Oaks ES
Roofing Program
Scope: |
Re-Roofing and Roof Related Work for Thousand Oaks Elementary School. |
Planning Estimate 1: |
$ 2,256,550 |
Start Date: |
March 2009 |
End Date: |
November 2009 |
Photo Gallery: |
Aerial Photos |
Architect: |
Wiss, Janney, Elstner Associates, Inc.![]() |
General Contractor: |
Beldon Roofing Company |
Project Summary: |
Bid Award Presentation (PDF) Bid Tab (PDF) |
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings (November 2006 through February 2007) for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs. Current Program Costs for each project are summarized in the 2007 Bond Budget Report.