Scope:
This project includes: will address critical HVAC requirements at the North East ISD Main Data Center located on the 1st Floor of the North East Education Center. The scope of work includes: (1) replacing and upgrading the existing Liebert HVAC system; (2) upgrading the fire suppression system; and (3) sub-partitioning the facility open space into logical compartments (Data Center Office Area, Main Technology Systems Area, Storage Area, Quick Copy Center, and Custodial Services Support Area) to optimize use of the Main Data Center Facility floor space.
Planning Estimate 1:
$ 1,000,000
Start Date:
January 9, 2012
End Date:
August 3, 2012
Architect/Consultant:
MEP Engineering, Inc.
Mechanical, Electrical, & Plumbing Engineering
General Contractor:
Mueller & Wilson, Inc.
Mueller & Wilson, Inc.
Project Summary:
Bid Award Agenda Item (PDF)
Bid Tab (PDF)


1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.