Bond Project: Specialty Projects
2003 Bond Program: Elementary School Clinics
Scope: |
Addition of a new clinic or expansion and renovation of existing clinic areas at four elementary schools to include a treatment area, examination area, restroom/shower facility and nurse's office. (Building addition: Fox Run and Oak Meadow. Expansion/Renovation: Redland Oaks and Windcrest) |
Planning Estimate 1: |
$ 1,085,000 |
Start Date: |
March 15, 2006 |
End Date: |
April 1, 2007 |
Architect: |
DeMunbrun Scarnato Associates, Inc. |
General Contractor: |
Baron-Long Construction, Ltd. |
Project Summary: |
Bid Award Agenda Item (PDF) Bid Tab (PDF) Project Summary (PDF) Site Plan (PDF) Floor Plans (PDF) |
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings (November 2006 through February 2007) for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs. Current Program Costs for each project are summarized in the 2007 Bond Budget Report.