2010 QSCB Project: Redland Oaks Elementary School
Re-Roofing and Roof-Related Work
Scope: |
This project addresses the Redland Oaks Elementary School Roof Replacement and Roof-Related Work Project which includes a total roof replacement area of approximately 87,531 sq. ft. |
Planning Estimate 1: |
$ 1,200,000 |
Start Date: |
June 13, 2011 |
End Date: |
September 10, 2011 |
Photo Gallery: |
Aerial Photos |
Architect: |
Wiss, Janney, Elstner Associates, Inc.![]() |
General Contractor: |
MRCO, Inc. |
Project Summary: |
Bid Award Agenda Item (PDF) Bid Tab (PDF) |