Project
Completed

2007 Bond Project: Montgomery ES Roofing Program

Scope:
This project replaces the north and east classroom wing addition roofs of the main building at Montgomery Elementary School measuring approximately 17,100 sq. ft.
Planning Estimate1:
$ 693,950
Start Date:
June 12, 2009
End Date:
July 30, 2009
Photo Gallery:
General Contractor:

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.