2003 Bond Project:
Madison High School
2003 Roofing Program
- Phase 1: Replaced the Auditorium Building roof (16,793 sq. ft.)
- Phase 2-A: Replaced the Vocational Building 1st floor roof area (12,564 sq. ft.) in concert with an Air Conditioning Rooftop Unit Replacement Project for the H and K Buildings
- Phase 2-B: Replaced the remainder of the H and K Building roof areas (53,314 sq. ft.).