2010 QSCB Project:
Krueger Middle School exterior curtain wall and Upgrades
Scope: |
The 2010 Qualified School Construction Bond Program includes funding to replace the exterior curtain wall system at the Krueger Middle School Auditorium. This wall system no longer provides a weather-resistant barrier, as a result of continued exposure to the elements and system age. The project will: (1) replace the existing brick veneer, inset windows, and spandrel panels with a new curtain wall system and stucco veneer exterior finish; (2) install new exterior doors and windows; (3) provide fabric-wrapped acoustical panels on the interior wall surface; and (4) paint the auditorium interior walls. |
Planning Estimate 1: |
$ 285,000 |
Start Date: |
June 2013 |
End Date: |
August 2013 |
Photo Gallery: |
Aerial Photos |
Architect: |
Marmon Mok |
General Contractor: |
Baron-Long Construction, Ltd. |
Project Summary: |
Bid Award Agenda Item (PDF) Bid Tab (PDF) |
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.