Project Details
Scope:
Construct an athletic field outdoor restroom and concession stand facility at the campus. The total facility program equals 1,175 sq. ft.
Planning Estimate 1:
$ 750,000
Start Date:
July 2013
End Date:
April 2014
Photo Gallery:
Aerial Photos
Architect:
Garza Bomberger & Associates
Garza Bomberger and Associates
General Contractor:
Guido Construction Company
Guido Construction Company
Project Summary:
Campus Improvement Project Construction Document Approval (PDF)
Schematic Design Presentation (PDF)
Construction Manager at Risk Selection Bid Award | Bid Tab
Schematic Design and Bid Delivery Method Approval Agenda Item

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.