Project
Completed

2003 Bond Project: Hidden Forest ES Roofing Program

Scope:
Roofing Program to replace the roof installed in 1978 at the Hidden Forest Elementary School main academic building over an area measuring approximately 47,441 sq. ft.
Planning Estimate1:
$ 856,174
Start Date:
December 2004
End Date:
April 2005
Photo Gallery:
Architect:
Edis Oliver and Associates, Inc.
General Contractor:
Mahone Roofing
Project Summary :

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.