2003 Bond Project: Encino Park Elementary School
Clinic & Kitchen Addition & Renovatons
Scope: |
This project will provide for the following: (1) construction of a new clinic (~637 sq. ft.), (2) conversion of the existing clinic into administrative office space and relocation /construction of the principal’s office to improve the overall function and layout of the campus administrative area, (3) expansion (~1,128 sq. ft.) and renovation of the existing kitchen facility including a new equipment package and (4) selective exterior/interior wall demolition and reconstruction at four school entrances to alleviate moisture/drainage concerns. |
Planning Estimate 1: |
$ 1,095,000 |
Start Date: |
January 15, 2006 |
End Date: |
October 31, 2006 |
Photo Gallery: |
Aerial Photos |
Architect: |
Lopez Salas Architects, Inc.![]() |
General Contractor: |
Baron-Long Construction, Ltd. |
Project Summary: |
Bid Award Agenda Item (PDF) Bid Tab (PDF) Project Summary (PDF) Site Plan (PDF) Floor Plans (PDF) |