Scope:
Existing nurse's clinic area will be expanded and renovated to District standards. 
Planning Estimate 1:
$ 292,791
Start Date:
August 2006
End Date:
September 2006
Photo Gallery:
Aerial Photos
Architect:
Garza Bomberger & Associates
Garza Bomberger and Associates
Architect:
O'Neill Conrad Oppelt Architects, Inc.
O'Neill Conrad Oppelt Architects, Inc.
General Contractor:
Bartlett Cocke General Contractors
Bartlett Cocke
Project Summary:
Bid Award Agenda Item
Bid Tab

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings (November 2006 through February 2007) for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs. Current Program Costs for each project are summarized in the 2007 Bond Budget Report.