2003 Bond Project:
Driscoll Middle School
Clinic Renovations
Scope: |
Existing nurse's clinic area will be expanded and renovated to District standards. |
Planning Estimate 1: |
$ 292,791 |
Start Date: |
August 2006 |
End Date: |
September 2006 |
Photo Gallery: |
Aerial Photos |
Architect: |
Garza Bomberger & Associates |
Architect: |
O'Neill Conrad Oppelt Architects, Inc. |
General Contractor: |
Bartlett Cocke General Contractors |
Project Summary: |
Bid Award Agenda Item Bid Tab |
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings (November 2006 through February 2007) for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs. Current Program Costs for each project are summarized in the 2007 Bond Budget Report.