Project: Churchill High School (Classroom Addition/Renovation)

New academic areas (new science department, new computer science lab, 18 new classrooms, and renovation of classrooms as needed), new HS administrative offices and nurse's clinic areas, new kitchen and cafeteria dining area, site work and hardscape improvements, upgrade band marching area, and construct satellite parking lot.
Planning Estimate1:
$ 24,160,000
Start Date:
July 2005
End Date:
May 2007
Photo Gallery:

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs.