2007 Bond Project: Bradley Middle School
Roofing Program


Project Completed
Project Details
Scope:
This project will provide for replacement of approximately 46,238 sq. ft. of existing facility roof with a new built-up roof, including overflow drains, additional roof insulation, curbs for mechanical equipment and minor piping modifications to facilitate the roof replacement.
Planning Estimate 1:
$ 1,491,600
Start Date:
May 21, 2010
End Date:
September 2010
Photo Gallery:
Aerial Photos
Architect:
WJE Engineers Architects
Wiss, Janney, Elstner Associates, Inc., Engineers Architects
General Contractor:
Beldon Roofing
Project Summary:
Bid Award Agenda Item (PDF)
Bid Tab (PDF)

1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings (November 2006 through February 2007) for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs. Current Program Costs for each project are summarized in the 2007 Bond Budget Report.