2007 Bond Project: Bradley Middle School
Roofing Program
Scope: |
This project will provide for replacement of approximately 46,238 sq. ft. of existing facility roof with a new built-up roof, including overflow drains, additional roof insulation, curbs for mechanical equipment and minor piping modifications to facilitate the roof replacement. |
Planning Estimate 1: |
$ 1,491,600 |
Start Date: |
May 21, 2010 |
End Date: |
September 2010 |
Photo Gallery: |
Aerial Photos |
Architect: |
WJE Engineers Architects![]() |
General Contractor: |
Beldon Roofing |
Project Summary: |
Bid Award Agenda Item (PDF) Bid Tab (PDF) |
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings (November 2006 through February 2007) for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs. Current Program Costs for each project are summarized in the 2007 Bond Budget Report.