2010 Project: Blossom Athletic Center
North East Tennis Center
Scope: |
Recoat 12 tennis courts; replace 2 asphalt courts with concrete due to soil conditions and provide lighting for the courts; resurface and recoat practice court; add perimeter fencing for security and crowd control; and add new windscreens. |
Planning Estimate 1: |
$ 452,925 (Funded from the Maintenance & Operations Program) |
Start Date: |
May 2010 |
End Date: |
August 2010 |
Photo Gallery: |
Aerial Photos | Construction Photos |
Architect: |
Rehler Vaugnh & Koone, Inc. |
General Contractor: |
Premier Courts |
1 The Bond Planning Estimate represents the original bond program costs developed during the bond planning meetings (November 2006 through February 2007) for each project and includes: Design Fees, Construction Costs, Technology Equipment and Installation, Furniture, Fixtures & Equipment and Construction Management Costs. The School Board "approved" construction budget can be found in the project Bid Award Agenda Item and represents any/all changes to the project resulting from the design development process and/or construction marketplace and inflation costs. Current Program Costs for each project are summarized in the 2007 Bond Budget Report.